1 This Power Automate Schedule Flow is not working as expected
1.1 Workflow Edit Mode
1.2 Workflow Ran at 10 PM at 25th July 2022
It should run on 7th Aug instead of 25 July.
2 This Power Automate Schedule Flow is working as expected
2.1 Workflow Edit Mode
2.2 Workflow Ran at 9 AM at 11th July 2022
Is something wrong with the configuration?
Thanks @David- , Correct me if I'm wrong, I need to RUN the Workflow manually for the first time if it is not triggered on time ( which I have provided in the recurrence connector). What I was thinking as well.
Based on your screen shots everything worked correctly. What you entered for the start in the configuration is the same as your screen shots. If you don't want the first run to be until 14 days after you set it up, then set the Start time to be that date. For example, the first one should have been set up with a start of August 7 instead of July 24. It will then recur again every 14 days after that start.
At least this is how all of my scheduled flows have worked...
@hachishti Just check one more day otherwise delete your trigger and add again.
Please 'Thumbs Up' the posts that helped you and 'Accept as Solution' if my post answered your question.