I need help to build a flow with the following conditions:
Wait for 1 day , check if(Status = New)-> reminder mail to EHS person to fill target date
Wait for 1 day, check if(Status = New)-> reminder mail to EHS person to fill target date
Wait for 1 day, check if(Status = New)->Mail to EHS manager
Pause until due date – 1, If(Status = Open)-> Send reminder mail to assigned person with due date
I need help with workflow number 1,2,3.
TIA
Take a look at the Delay and Delay until actions - they are the key to what you are trying to do. Also, remember that a Flow can run for a maximum of 30 days - if your due date is more than 30 days out, you cannot approach it this way.