Hi @Vints ,
Please first customize the sharepoint form in PowerApps, then modify the DefaultDate of Material arrive date picker as follows.
The date will changed as the supplier changes.
Switch(
SupplierComboBoxName.Selected.Value,
"glass- 2 days", DateAdd(Now(),2,Days),
"hardened glass -9 days", DateAdd(Now(),9,Days),
"glass with film - 4 days", DateAdd(Now(),4,Days),
"painted glass - 10 days",DateAdd(Now(),10,Days),
"mirror - 3 days", DateAdd(Now(),3,Days),
"sandblasted glass - 6 days" ,DateAdd(Now(),6,Days)
)
Hope this helps.
Sik