Hi good people,
I have been trying to create a flow that would allow tasks to be pushed from Project to Planner when I publish a project, with new tasks added and old ones updated with new dates. Right now I'm able to get tasks into Planner, but not update, and I end up with duplicates if I run it again, instead of updates....
Basic steps below:
When a Project is Published --> List Plans for a Group --> Condition: (Planner) Plan Name = (Project) Project Name --> If yes: (Project) List Tasks with Project ID -> (Planner) List Tasks with value ID --> Condition: (Planner) Task Title = (Project) Task Title --> If yes: Update a Task /// If no: Create a Task
Image references are attached, I've searched all over for a solution to this, but each one usually involved Excel or Outlook, but not Project. Any help would be much appreciated!