Looking for help still pretty new to the power automate process.
I have been asked to make a workflow that looks for overdue tasks in a specific planner. A notice is supposed to go to the person that it's overdue by x days. A second notice is supposed to go to the person + their supervisor if the task still isn't completed.
This is kind of what I've got so far from poking around the webs.
Any help or right direction would greatly be appreciated. Thank you in advance.
Ok - this currently works for an overdue task from planner. It's not terribly pretty but it works (so far). What I need it to do now is to send an escalation email for x days that it isn't completed.
The task planner is being used by members outside of my team for things like weekly inspections, daily tasks and such.