Power Platform Community / Forums / Power Automate / More Project Online ob...
Power Automate
Answered

More Project Online objects

(2) ShareShare
ReportReport
Posted on by Microsoft Employee

I'm interested in creating several flows to reflect actions taken or status based on the passage of time (e.g., tasks approaching a deadline) in Project Online. How do we go about connecting to additional fields in the Project Online data model (including custom fields)?

Categories:
I have the same question (0)
  • Community Power Platform Member Profile Picture
    Microsoft Employee on at

    Ken, you say more objects...so you have gotten some flows working with project online events or data?  Do you know of documentation or any blogs on this topic?

  • Community Power Platform Member Profile Picture
    Microsoft Employee on at

    Hi Chad -

    There are two Project Online templates here that I've used. They're a good starting point but I'd love some additional capabilities.

  • Verified answer
    Lalit Profile Picture
    Microsoft Employee on at

    Hi,

     

    Here are some templates on projet online.

    https://flow.microsoft.com/en-us/search/?q=project+online. You can start with these.

     

    You can also create a flow from scratch using "Project online".

    Here is a snapshot of project online supported triggers and actions. I can add further more detail if you can describe the scenario you are trying to achieve. 

     

    Project online.PNG

  • Community Power Platform Member Profile Picture
    Microsoft Employee on at
    good deal. thanks
  • Community Power Platform Member Profile Picture
    Microsoft Employee on at
    Thanks Ken
  • Community Power Platform Member Profile Picture
    Microsoft Employee on at

    Thanks, Lalit. I'm interested in looking at project schedules when they are published and checked-in and checking, for example, if there are tasks without predecessors or that haven't a Baseline0 value, and then sending an email. Can that type of thing be done?

  • villev Profile Picture
    7 on at

    Hello, I have same requirements as Ken43708.

    I would need to use Project Custom Fields and Task completion etc in Flows.

    This is _not_ possible with the templates and actions provided today (or in the answe that is marked as a solution).

     

    Can you please take this in the backlog?

  • Andy_PF Profile Picture
    7 on at

    Good Day All,

     

    I think being able to get at Enterprise Custom Fields in PWA would be a powerful option, also being able to create a flow that will sync SharePoint lists with EFC lookup fields would also be incredible useful.

     

    Some idea on roadmap for Flow and Project Online capability would be nice. Opportunity to advance Flow and Project Online to an incredibly powerful partnership.

     

    Regards

     

    Andy.

     

  • PinkFloyd Profile Picture
    Microsoft Employee on at

    Also to bring over tasks assignments and resource information from Project Online to Planner. Does this change with the project service and the CDS platform?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Kudos to our 2025 Community Spotlight Honorees

Expanding mentorship, skilling, and AI innovation

Congratulations to the June Top 10 Community Leaders!

These are the community rock stars!

Leaderboard > Power Automate

#1
David_MA Profile Picture

David_MA 246 Super User 2026 Season 1

#2
11manish Profile Picture

11manish 176

#3
Haque Profile Picture

Haque 157

Last 30 days Overall leaderboard