I have a column called supplier in SharePoint, in that column i have these choices
glass– 2 days
- hardened glass – 9 days
- glass with film – 4 days
- painted glass – 10 days
- mirror – 3 days
- sandblasted mirror – 6 days
based on choice which was choosed for the order no, it should automatically update the date column based on supplier shoosen. example today is 28/9/2020 order no PR001 use glass as supplier was choosen, then in material arrival date column it should be as 30/9/2020.
an automatic selection of date column based on choice from the supplier column