I'd to create a planned finish column based on the input of planned start date and duration in a model driven app.
However, the syntax reports an error, and I couldn't get my head around it. Would you please shed some light on it?
Thanks in advance!
Jane
Hi @OctMonica ,
Because StartOfWeek is not recognized in the formula column, it resulted in an error. As a workaround, please try
If( Weekday('Planned Start')=1, 7, Weekday('Planned Start')-1 )
Instead of
Weekday('Planned Start',StartOfWeek.Monday)
Best Regards,
Bof
Thanks Bof, I tried but it still pops error message saying dateadd has invalid arguments.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our community stars!
Expanding mentorship, skilling, and AI innovation
These are the community rock stars!
Stay up to date on forum activity by subscribing.
WarrenBelz 358 Most Valuable Professional
11manish 214 Super User 2026 Season 2
Mohsin Ali 185