Power Platform Community / Forums / Power Automate / Capture date from task...
Power Automate
Answered

Capture date from task updates in project planner board

(1) ShareShare
ReportReport
Posted on by 8
Hi community, I would like to build a power automate flow to help me measure the throughput time in our project planner board.

I would like to capture the date when the task is moved to a new bucket in project planner board. That date shall be moved to an excel sheet, so I can follow it up.
 
I can only trigger on task creation and not modification. 
 
Thanks,
Lizett
Categories:
I have the same question (0)
  • Verified answer
    Michael E. Gernaey Profile Picture
    53,974 Moderator on at
    Hi
     
    The unfortunate answer is there is not a trigger for this. So you would have to constantly check planner and check each task to see if it changes buckets.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Users!

Kudos to our 2025 Community Spotlight Honorees

Congratulations to our 2025 community superstars!

Congratulations to the March Top 10 Community Leaders!

These are the community rock stars!

Leaderboard > Power Automate

#1
Haque Profile Picture

Haque 552

#2
Valantis Profile Picture

Valantis 388

#3
11manish Profile Picture

11manish 375

Last 30 days Overall leaderboard