web
You’re offline. This is a read only version of the page.
close
Skip to main content

Announcements

News and Announcements icon
Community site session details

Community site session details

Session Id :
Power Platform Community / Forums / Power Automate / Automatic Planner Task...
Power Automate
Answered

Automatic Planner Task Creation - unable to fill "Assigned by" field

(0) ShareShare
ReportReport
Posted on by 24

I built a flow that creates a planner task every time a record is inserted in a sharepoint list.
All the tasks should all be assigned to the same user, but they can be assigned by different users.
How can I set the value "Assigned by", to notify him the task's completion?

Thank's

Marco

 

Categories:
I have the same question (0)
  • Ed Gonzales Profile Picture
    4,531 Most Valuable Professional on at

    @marpisa 

    Hi there...  So, I'm wondering if the Assigned By is coming from the Planner connection, and may not be editable.  I don't see any way with the regular Planner connectors.

     

    Have you already tried with the Graph API?

     

    Keep us posted.

    -Ed-

     

    If you liked this reply, please give it a thumbs up! If this reply has answered your question or resolved your challenge, please consider marking it as a Solution. This helps other users find it more easily via search.

  • v-bacao-msft Profile Picture
    Microsoft Employee on at

     

    Hi @marpisa ,

     

    If you use Create a task action to create a task and assign the task to the specified user, then assigned by user is the user who configured the action.

     

    In addition, if you want to notify the user who assigned the task when the task is completed, you can refer to the following configuration:

    167.PNG

    Details in Apply to each:

    168.PNG

    Hope this helps.

     

    Best Regards,

  • marpisa Profile Picture
    24 on at

    Hi,

    I use "Create a task action" inside a Flow. The assigned by user is my account as Flow Owner.

    But If is the User1 to create the sharepoint record, i want that the [assigned by user] value is User1 and not My account.

    In the "Create task" there isn't a way to compile the "Assigned By" value, and ther is not (at least I didn't find it) a way to edit this value in a second moment.

    I can get this value only when the task is completed....

     

     

  • Verified answer
    v-bacao-msft Profile Picture
    Microsoft Employee on at

     

    Hi @marpisa ,

     

    Yes, as I described before, Create task action cannot specify Assigned by, only Assigned to.

    And assigned by will be the user who creates this Flow. MS Flow does not currently support editing assigned by.

    In addition, if you need to notify assigned by when the task is completed, please refer to the method provided in my previous post.

     

    I hope that helps.

     

    Best Regards,

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Users!

Kudos to our 2025 Community Spotlight Honorees

Congratulations to our 2025 community superstars!

Leaderboard > Power Automate

#1
Haque Profile Picture

Haque 293

#2
David_MA Profile Picture

David_MA 262 Super User 2026 Season 1

#3
Expiscornovus Profile Picture

Expiscornovus 223 Most Valuable Professional

Last 30 days Overall leaderboard