Hi all,
I need some assistance with a timeout approval flow.
So basically i set a time out at "wait for approval50K", and if the original approver does nothing the right branch will be triggered.
Although the flow was successfully completed, the last action of "update item 3" did not get triggered.
At the left branch, i put in a compose action to do nothing, at "update item 3" i selected the below.
Any idea where it had went wrong? Thanks!
Its the use of the Terminate in the right branch. When that runs the entire flow will terminate, so it will never reach Update 3. If you want it to run to completion, but don't want to update the item then move the Update 3 into the left branch where the compose is now. Then put a compose where the Update 3 was and remove the Terminate.
WarrenBelz
146,605
Most Valuable Professional
RandyHayes
76,287
Super User 2024 Season 1
Pstork1
65,946
Most Valuable Professional