Posted on by 13

G'day

 

I am having trouble trying to find a way to make Excel more dynamic. 

Here is the use case

I need to have all Planner tasks that are assigned to me available for my manager to quickly look at so they can see my current workload without having to dig through Planner itself.

 

What I wish to do is have all my tasks from Planner populate an Excel spreadsheet which will everyday dump what my tasks are.

The catch is I also need it to Update or at least delete the old information. so everyday I get a fresh dump of what is on my planner board without it doubling up in the spreadsheet.

 

I can create a macro to erase info from the spreadsheet every day or use Excel to hide information with a certain date stamp but that becomes difficult to manage and rather clunky.

 

This is the flow i have now which does not fully work as it fails when it comes to the Row ID im not sure how to set that field to get it to always look at all the rows and update all of them. All I can get so far is the dump of all my tasks over and over so they duplicate everytime the flow runs. I put the Current time in the flow as a way to work out when it was dumped so i can see which is a duplicate.

Excel Flow part 1Excel Flow part 1Excel Flow part 2Excel Flow part 2

Any advice or solution would be very welcome

 

Cheers

Tristan

Categories:
I have the same question (0)
  • Verified answer
    v-yuazh-msft Profile Picture
    Microsoft Employee on at

    Hi @TristanUTS,

     

    If you want to update or delete the old information in the excel table will the tasks from Planner,you could delete the rows in the excel table firstly and then insert the tasks from Planner to the excel table, and the screenshot of the flow as below:

    Capture.PNG

     

    Best regards,

    Alice

  • TristanUTS Profile Picture
    13 on at

    Hi @v-yuazh-msft

     

    Thank you so much for your reply that got it working as I needed it to.

     

    Cheers

    Tristan

  • Community Power Platform Member Profile Picture
    Microsoft Employee on at

    Hello Alice,

     

    I did this (but listing all tasks in plan) and it was working great until I hit over 400 tasks in my plan. now it will only pull 400 tasks. Have you run into anything like this?

     

    Cheers,

     

    Shiann

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Users!

Kudos to our 2025 Community Spotlight Honorees

Congratulations to our 2025 community superstars!

Leaderboard > Power Automate

#1
David_MA Profile Picture

David_MA 262 Super User 2026 Season 1

#2
Haque Profile Picture

Haque 227

#3
Expiscornovus Profile Picture

Expiscornovus 225 Most Valuable Professional

Last 30 days Overall leaderboard