Hi Experts,
 
In excel i am having date format as bellow :

 
But Power automate flow is showing as below and failed :
Here i have applied a condition like if TaskID in excel file is blank then Create a new task , if not then update the task into a MS Planner.
 
 
 
Please help to achieve this requirement .
 
thanks DK
Categories:
I have the same question (0)
  • David_MA Profile Picture
    12,982 Super User 2025 Season 2 on at
    What is the relationship between the date in your Excel spreadsheet and the action of updating a task? The Update a task action says it failed because it could not find the task you specified to update, which would be based in its ID and has nothing to do with the dates in your Excel spreadsheet. Maybe you're trying to update it based on the plan ID rather than the task ID.
  • DA-21020540-0 Profile Picture
    11 on at
    @David_MA  Ohh ok but I can see the taskID is available in excel sheet as below :
     
     
     
    Below the flow portion :
    As per above excel sheet, taskID is not blank , so the condition is NO , it should update the data where i have updated the new data (Updated new due date in all the rows)
     
     
    Let me know if you need more details .
     
     
    Thanks
    DK
  • Suggested answer
    David_MA Profile Picture
    12,982 Super User 2025 Season 2 on at
    Looking at this again, if the task IDs exist and are accurate, then the issue is with the bucket ID. Since you only show the flow run in your screen shot and not the configuration of the action, I cannot be sure. But, in the bucket you should be entering a GIUD. If you are entering Plan 2025 for the value of the bucket ID, that is what cannot be found.
     
    To get the bucket IDs, you can use a Graph API call: GET https://graph.microsoft.com/v1.0/planner/plans/{plan-id}/buckets. If you log into the Graph API explorer at Graph Explorer | Try Microsoft Graph APIs - Microsoft Graph you can run this query to get the IDs of the buckets in the plan.
     
     
     
  • DA-21020540-0 Profile Picture
    11 on at
     
     
    Also in Update a task V2 there is no other fields are available to update into MS Planner , like Assignee Name , Progress .. 
     
     
     

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Forum hierarchy changes are complete!

In our never-ending quest to improve we are simplifying the forum hierarchy…

Ajay Kumar Gannamaneni – Community Spotlight

We are honored to recognize Ajay Kumar Gannamaneni as our Community Spotlight for December…

Leaderboard > Power Automate

#1
Michael E. Gernaey Profile Picture

Michael E. Gernaey 525 Super User 2025 Season 2

#2
Tomac Profile Picture

Tomac 324 Moderator

#3
abm abm Profile Picture

abm abm 232 Most Valuable Professional

Last 30 days Overall leaderboard