Hello helpful people!
I've been attempting to create a flow for a while now and have no success.... Although it says it ran successfully, the results are not there!
Anyway, I currently have 2 flows.
1st: I fill out a form which sends the information to a SharePoint list.
2nd: The creation of a new item in SharePoint List triggers a Planner Task creation.
The idea is the Tasks can be used in a user-friendly dashboard and then the SharePoint list gives me the possibility to compile more detailed reports all from information that I enter into a form.
What I need and it will be so useful! is to utilize the trigger "When a Task is Completed" and be able to update the SharePoint List with whoever was assigned to that task.
There are options for this and it seems doable, I just keep hitting obstacles! Can't figure it out. SOS please help!
Let me know if I can upload screenshots or give more information.