I have created a Power Automate Flow that is triggered by a form submission and then creates and updates a task in Planner. The dynamic content for the answer to "Event Date" is used to populate the "Due Date" in the Planner task. The Planner task due date is showing as a day earlier than what is supplied in the form answer.
I have checked the time zone of all platforms connected with this flow and they all match. When I test the flow and view the outputs, everything appears correct. The date response from the form is exactly equal to the due date output for the task.
I have attempted adding functions and steps to the flow to ensure that all the dates are in the same time zone, but those solutions do not help.
Form Response Output:
Planner Task Due Date Output:
Planner Due Date: