Hello, I have been creating flows for automating project management tasks. Oddly enough, when I use triggers from Planner, I can create flows that retrieve my project's (in project online) list of tasks, dates, etc. However, when using any Project Online trigger (e.g., when a new task is created), I get the error statusCode: 403, and odata.error code: 20010, with "Access Denied" value.
I tried creating different flows and using other triggers, but I always get the same Access Denied. Is that truly an access problem, and if so, at which end? The IT in my company says I should have the proper permissions to Project Online and Power Automate. If I can pinpoint which access I am missing, they can grant it.
Thanks!
Should any of you have the same problem, I did not have the global permission "Access Project Server Reporting Service" activated. After granting the permission, the connection worked.
As a side note, Project Online was configured in its default setting (Sharepoint permission mode) and it needs to be switched to project permission mode. Then it allows more granular permissions and that server project reporting service becomes available.