I am using the Microsoft Project Power Apps Model Driven App and have customized it out extensively for my companies use.
However I have seem to run into a bug when adding projects. I have already added 257 projects no issue. However now when adding new projects it will say "Calendar Id: Required fields must be filled in." and I know how to unlock it to it's not read only however in the past new projects would auto populate this information.

Also previously these fields on the form were hidden and I had never had to input this information before but I unhid them because I was also having an issue with the "hours per day" not being filled out. Again this hadn't been an issue before.
Thanks.