Hi,
Apologies the subject header might not make much sense as it stands. Basically I'm running a system which requires it to calcuate how many work days there are between two dates in a SP List. That's all fine, I've got a StartDate / EndDate / DaysExWE which is calculated column which strips out the weekends. However what I need to do is make sure none of those days fall on a bank holiday.
I was going to have a separate SP List but I'm stuck with the logic of how I would do an array in power automate presumably with a 'Do Until' loop. And when I mean stuck with the logic, I don't even know where to start!
Thanks
David