What’s happening?
The system is not processing the expected receipt date correctly in purchase order lines within Dynamics 365 Business Central, potentially due to configuration problems with supplier settings.


Troubleshooting:
Check Supplier Configuration:

  1. Navigate to the suppliers tab.
  2. Select the desired supplier.
  3. Click on Related > Purchases > Objects.
  4. In the Lead Time Calculation section, specify the number of days it will take for the supplier to ship the product.
Verify Lead Time Calculation:
  1. If there is a requested receipt date on the purchase order line, use the following calculations:
    • requested receipt date - lead time calculation = order date
    • requested receipt date + inbound warehouse handling time + safety lead time = expected receipt date
  2. If no requested receipt date is specified, base the calculation on the order date:
    • order date + lead time calculation = planned receipt date
    • planned receipt date + inbound warehouse handling time + safety lead time = expected receipt date
Testing:
  1. Create a purchase order with the supplier and item, using today's date to verify that the system processes the expected receipt date correctly.
Environment Check:
  1. Ensure that the testing is done in a clean environment without any extensions that might interfere with the calculations.