If I have an approval with loops running and other condition, Will they last for 30 days just like the approval?
Hi @Anonymous ,
I believe 30 days is the hard limit for a single flows and any actions.
--------------------------------------------------------------------------If I have answered your question, please mark my post as a solutionIf you have found my response helpful, please give it a thumbs upConnect on LinkedIn
Is that the default or do I have to set it through settings?
@Anonymous
There is no setting that impacts how long a Flow will run - an instance of a Flow will run for a maximum of 30 days as mentioned by @eric-cheng
@ScottShearer
There is a setting in each cell of the flow as show in the screenshot below
Do I have to set the flow to P30D in the timeout setting or is it set to 30 days by default?
@Anonymous - By default, its 30 days as mentioned by @eric-cheng and @ScottShearer
https://docs.microsoft.com/en-us/power-automate/limits-and-config#run-duration-and-retention
The timeout setting that you are referring to is specific to the action on which it is set. This setting is frequently used in concert with the run after functionality. There is no setting that controls the timeout of the overall Flow - it is 30 days.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our community stars!
Expanding mentorship, skilling, and AI innovation
These are the community rock stars!
Stay up to date on forum activity by subscribing.
11manish 298 Super User 2026 Season 2
Mohsin Ali 289
Henil 125