Power Platform Community / Forums / Power Automate / Create planner task fr...
Power Automate
Answered

Create planner task from Microsoft project (it only creates 3 instances and stops)

(0) ShareShare
ReportReport
Posted on by 8

Hello Everyone,

 

I'm having an issue creating new tasks from project to planner. I can have the flow trigger but it only completes 3 tasks. If I just try 4 it only creates the 3 first tasks.  Below is the flow, It seems like a very simple flow but not creating all of them is not helpful. I've peeked at the code and it is supposed to run every five minutes. I was hoping that it would pick up the rest, but it does not. I've left it overnight and it still does not work. Any help would be appreciated.

 

Thank you 

triggs_0-1633613409760.png

 

Categories:
  • Expiscornovus Profile Picture
    34,005 Most Valuable Professional on at

    Hi @triggs,

     

    Are the tasks all coming from the same project?

     

    Btw, have you already tried the new version of that trigger action? There is a v2 in preview.

     

    whenanewtaskiscreatedv2.png

  • triggs Profile Picture
    8 on at

    @Expiscornovus ,

     

    Yes, they are coming from the same project.

    I have tried both versions as well.

     

    Thanks, 

  • Expiscornovus Profile Picture
    34,005 Most Valuable Professional on at

    Hi @triggs,

     

    Just to double check. The Project is published, there is not a publish project job stuck in the PWA queue?

     

    Can you reproduce this with a different project as well?

  • triggs Profile Picture
    8 on at

    @Expiscornovus 

     

    Yes the project is published, and there is no job stuck in the que

     

    it does this for all projects.

     

    THanks you

  • Verified answer
    Expiscornovus Profile Picture
    34,005 Most Valuable Professional on at

    Hi @triggs,

     

    I just managed to reproduce it on one of my demo tenants. So, that sounds like a bug. I would advise to either contact Microsoft support via a service request in your tenant. See if they can help you with this?

     

    Btw, for completion below were my repro steps.

     

    1. Created 4 new tasks in a new project. Saved it, Published it and check-in. 

     

    projectonline_bug02.png

     

    2. Get three flow runs for task Test, Test01 & Test02. It seems to ignore the 4th task.

    projectonline_bug01.png

     

     

  • triggs Profile Picture
    8 on at

    Thank you, I just wanted to make sure I'm not crazy, lol.

     

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Kudos to our 2025 Community Spotlight Honorees

Expanding mentorship, skilling, and AI innovation

Leaderboard > Power Automate

#1
11manish Profile Picture

11manish 317 Super User 2026 Season 2

#2
Mohsin Ali Profile Picture

Mohsin Ali 247

#3
Henil Profile Picture

Henil 117

Last 30 days Overall leaderboard