Power Automate - Building Flows
Answered

Dynamics 365

(0) ShareShare
ReportReport
Posted on by

Hello guys,

 

I was trying to create a flow with the planner and dynamics 365.

 

I want to create a record in the tasks entity in the Dynamics 365 when the task is created in the planner.

 

Does anyone try that? Any ideas? 

 

I am getting this error: "Property ismapiprivate is not valid for write"

I have the same question (0)
  • PieterVeenstra Profile Picture
    13 on at
    Re: Dynamics 365

    Can you show the flow run history?

     

    Something like this:

     

    FlowHistoryDynamics365.PNG

     

    For me it worked so most likely you are setting different fields or fields with different values..

  • Community Power Platform Member Profile Picture
    on at
    Re: Dynamics 365

    {
      "subject""Test #4 Dynamics",
      "description""Test #4 Dynamics",
      "scheduledend""2018-05-04T10:00:00Z",
      "actualdurationminutes"120,
      "_prioritycode_label""Normal",
      "isregularactivity"true,
      "actualend"null,
      "actualstart""2018-04-30T10:00:00Z",
      "isbilled"false,
      "isworkflowcreated"false,
      "percentcomplete"50,
      "scheduledstart""2018-04-30T10:00:00Z",
      "_instancetypecode_label""Not Recurring",
      "_deliveryprioritycode_label""Normal",
      "ismapiprivate"false,
      "leftvoicemail"false
    }

     

     

  • Community Power Platform Member Profile Picture
    on at
    Re: Dynamics 365

    flow_request.PNG

  • PieterVeenstra Profile Picture
    13 on at
    Re: Dynamics 365

    I tried replicating  the same but I'm not seeing a property "ismapiprivate" Is that a cusotmisation on your Task entity?

     

     

  • Community Power Platform Member Profile Picture
    on at
    Re: Dynamics 365

    No, there is none. 

     

    https://msdn.microsoft.com/en-us/library/mt607619.aspx

     

    You can see from that link that such field exists.

     

    "ismapiprivate"

     

    ismapiprivate

    Edm.Boolean

    Description: For internal use only.

    Inherited from: activitypointer EntityType

  • PieterVeenstra Profile Picture
    13 on at
    Re: Dynamics 365

    I thought you were creating a Task but on my task entity that field doesn't exist.

    Isprivate.PNG

     

     

     

    I tried creating an Activity but it isn't possible to create and activity as I'm getting:

     

    message""The 'Create' method does not support entities of type 'activitypointer'.",

     

     

     

     

     

     

     

  • Community Power Platform Member Profile Picture
    on at
    Re: Dynamics 365

    I am creating a task also, and I also do not have such field in my Task entity. I do not know where it is coming from. 

     

    I had the the same error: "The 'Create' method does not support entities of type 'activitypointer'.", when I tried creating an activity so I switched to Task.

     

    Anyway, thanks for your help.  

     

    I will search further. 

  • v-xida-msft Profile Picture
    on at
    Re: Dynamics 365

    Hi @Anonymous,

     

    Could you please share a full screenshot of your flow's configuration?

     

    I have made a test on my side and don't have the issue that you mentioned. In addition, I could not find the ismapiprivate Property within the "Create a new record" action of Dynamivcs 365 connector. My flow's configuration as below:6.JPG

    The flow works successfully as below:7.JPG

     

     

    The error message told that the ismapiprivate Property is not valid for write. Based on the article that you provided, the ismapiprivate Property is a internal property in Tasks entity, we could not edit it or assign a value to it within Microsoft Flow.

     

    Please take a try to clear cache of your browser and re-create your flow to check if the issue is solved. If you have any further discovery in this issue, please let me know here.

     

    Best regards,

    Kris

     

  • hoanghiem Profile Picture
    2 on at
    Re: Dynamics 365

    Hi, I guess we got this message because we create an Activity then we switch to Task. 

     

    When I first created Activity. I got error: The 'Create' method does not support entities of type 'activitypointer'. -> we need to define specificly as it is a Task/Phone call/Appointment.

    After I updated that step to 'Create a Task' and got the same error "Property ismapiprivate is not valid for write". Look like it carrys on that property from Activities to Task. 

     

    I recreated the flow with a brand new 'Create a Task' step and it works. Hope it helps.

  • Verified answer
    Community Power Platform Member Profile Picture
    on at
    Re: Dynamics 365

    Hello everyone,

     

    Thanks for replies. In tthe end I solved the problem by recreating MS Dynamics environment. It seems that mine was broken.

     

     

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Chiara Carbone – Community Spotlight

We are honored to recognize Chiara Carbone as our Community Spotlight for November…

Leaderboard > Power Automate

#1
Michael E. Gernaey Profile Picture

Michael E. Gernaey 659 Super User 2025 Season 2

#2
Tomac Profile Picture

Tomac 386 Moderator

#3
chiaraalina Profile Picture

chiaraalina 290

Last 30 days Overall leaderboard