Planner - List Tasks no longer listing completed tasks

(0) ShareShare
ReportReport
Posted on by 5

Hi everyone, 

 

Is it possible that in recent days or possibly weeks that the Planner - List tasks connector has broken? I have a flow that counts Total tasks (Not completed + Completed) and another count of just tasks "Not Completed" so that I can calculate the overall percentage of completed task relative to total tasks. However, I have made no change to my flow and all of a sudden my total tasks always equal the same amount of incomplete tasks. 

 

I created a new flow to test and the results are exactly the same. I also tried to filter just tasks that are 100% complete but I get zero results. 

 

I would post a screenshot but I can't find a way to post it in this message without first hosting it online. 

 

Any insight would be appreciated. This is causing me a lot of grief cause my superiors think I haven't been completing any tasks from the look of our SharePoint report. 

Categories:
  • Rohit Sharma354 Profile Picture
    Microsoft Employee on at

    Hello,

     

    I tried creating a simple flow to list the tasks and it returned all tasks (completed + not completed).

     

    Please check if group ID and Plan ID of the completed tasks is same, just in case.

    The List tasks action returns the list of tasks based on these two values, and if completed tasks are mapped to other plan, then it may get excluded from the output.

     

     

  • SylvainRL Profile Picture
    5 on at

    I'm starting to think that my Plan is corrupt. I tried to pull the same info from another plan and I got the proper numbers. Now I'm going to have to try and figure out how to fix the Planner Plan and I have no clue what, if anything, can be done. 

  • SylvainRL Profile Picture
    5 on at

    Actually, after further inspection, I realized that the issue is caused by a 400 task cap imposed on the "List Tasks" action. My plan has nearly 1000 tasks and it will just keep growing. I thought about automatically deleting the tasks as they are completed but that's not possible with a non premium license from what I can tell. Does anyone know of any way around the 400 task limit? I'm at a loss. Planner is pretty much the center of all my processes and there has been so many hours invested in writing them all and at this point It's no longer feasible to rewrite them.

     

    Any suggestions would be greatly appreciated.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Kudos to our 2025 Community Spotlight Honorees

Expanding mentorship, skilling, and AI innovation

Leaderboard > Power Automate

#1
11manish Profile Picture

11manish 243 Super User 2026 Season 2

#2
David_MA Profile Picture

David_MA 211 Super User 2026 Season 2

#3
Mohsin Ali Profile Picture

Mohsin Ali 190

Last 30 days Overall leaderboard