due date needs to be on workdays only

(0) ShareShare
ReportReport
Posted on by 28

Hellimage.pngo all,

 

I'm building a flow that creates a Planner task. User has 5 workdays to complete the task. So, therefor the due date most always be a workday. 

Who can help me with this?

 

Thanks!

Categories:
  • v-litu-msft Profile Picture
    Microsoft Employee on at

    Hi @MargeNL,

     

    If is the due date always 5 days? If it always 5 days, you can add two more days at the End date field.

    If it not always 5 days, you can judge the start date whether is Thursday or Friday by using the dayOfWeek() function, if it is, add two more days, if not, no need to add.

     

    Best Regards,
    Community Support Team _ Lin Tu
    If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

  • MargeNL Profile Picture
    28 on at

    Thank you. Sometimes things are so simpel!

  • MargeNL Profile Picture
    28 on at

    Hold on.

    I get the two extra days in case of 5 workdays.

     

    How do I use the dayOfWeek function in case of 3 workdays?

    Thanks for your patience.

  • v-litu-msft Profile Picture
    Microsoft Employee on at

    Hi @MargeNL,

     

    If the due date is 3 workdays, you can also judge the start day whether is Thursday or Friday.

    If it is, End date = Start Date + 5 days.

    Best Regards,
    Community Support Team _ Lin Tu
    If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

  • MargeNL Profile Picture
    28 on at

    Thank you, I understand that.

    What I would like to learn/know is how to have the Flow Judge whether the start day is a Thursday or Friday.

     

  • Verified answer
    MargeNL Profile Picture
    28 on at

    Yes! I think I worked it out.

     

    Used this: 

    if(or(equals(dayofweek(utcNow()),4),equals(dayofweek(utcNow()),5)),addDays(utcNow(),5),addDays(utcNow(),7))
     

     

     

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Kudos to our 2025 Community Spotlight Honorees

Expanding mentorship, skilling, and AI innovation

Leaderboard > Power Automate

#1
Mohsin Ali Profile Picture

Mohsin Ali 423

#2
11manish Profile Picture

11manish 308 Super User 2026 Season 2

#3
M Bilal Khan Profile Picture

M Bilal Khan 177

Last 30 days Overall leaderboard