Re: due date needs to be on workdays only
Hi @MargeNL,
If is the due date always 5 days? If it always 5 days, you can add two more days at the End date field.
If it not always 5 days, you can judge the start date whether is Thursday or Friday by using the dayOfWeek() function, if it is, add two more days, if not, no need to add.
Best Regards,
Community Support Team _ Lin Tu
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.