Adding Days to a date pulled from a forms response

(0) ShareShare
ReportReport
Posted on by 8

My current pickle - I am a teacher and have quite a few graders working for me to grade in quite a few classes. We use planner in teams so they can let each other know who is grading/responsible for which assignment. The classes we teach occur regularly and always have due dates based on the start date of the course. 

 

I have set up a Form with a date question "Start Date of Course" and a choice question to pick the class that is running.

 

My goal is to use the form (for now, this will be in salesforce eventually) anytime a new class starts to create items in Planner; specifically it is set to create a bucket (the class) and all associated assignments (tasks) w/ due dates as the graders are to grade on a FIFO system based on due date.

 

I keep hitting an error when getting to the "Create a Task" step because of the due date.

 

In the due date field, I can not figure out how to use the "Start date of course" (a response from the form in date format

Machine_0-1611611723422.png) with the "addDays" function.

When setting up the FORM, I did make sure to use the "Date" feature on the question. If I use the "Start Date of Course" content directly in the "Due Date Time" under "Create a Task" it works fine; but I can not figure out how to change that date. 

Machine_1-1611611907375.png

 

Categories:
  • Verified answer
    Gopala_Krishna Profile Picture
    1,495 on at

    @Machine 

    On the addDays function you can also specify the format of the resulting value, addDays function accepts three parameters 1 - The timestamp to which the days have to be added,2- number of days to add,3- format in which the resulting value has to be in. 

     

    Let us consider that I am using the addDays function and I want my result to be in format MM-dd-yyyy then I will specify this as a third parameter of the function.

     

    Also the planner expects the date values to be in full time format which is yyyy-MM-ddThh:mm:ss.ssZ

     

    To ease the process you can use the default action from power automate

    Gopala_Krishna_0-1611682321460.png

     

    This will directly give you the desired result, for more information related to the planner action please check - Planner - Connectors | Microsoft Docs

     

    For information related to timezone format and how to setup - ISO 8601 - Wikipedia

     

    If the information shared helps you, please consider giving a thumbs up 👍 and mark solution as resolved.

  • Machine Profile Picture
    8 on at

    @Gopala_Krishna I ended up using the default action as you suggested. With the number of assignments and due dates, I was hoping keep it within the create a task action as a way to keep the automation a little cleaner. Just have to keep good/better track of which date I'm calling with the default action I suppose.

    Thank you for the reply! 

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Kudos to our 2025 Community Spotlight Honorees

Expanding mentorship, skilling, and AI innovation

Leaderboard > Power Automate

#1
11manish Profile Picture

11manish 302 Super User 2026 Season 2

#2
Mohsin Ali Profile Picture

Mohsin Ali 263

#3
Henil Profile Picture

Henil 115

Last 30 days Overall leaderboard