Hello, I have a Sharepoint list that is designed to track cases. I have also built a Flow that is designed to send an email when the case is due in 2 days (i.e. [Days Until Due] = 2).

The [Days Until Due] field is a calculated field in SP, basically =89-(TODAY()-[Date Change Authorised]).
[Date Change Authorised] is a Date field, manually entered.
My Flow has the condition [Days Until Due] contains string(2), however the email is triggered if the [Days Until Due] is 2, 12, 22, 42, etc.

I tried [Days Until Due] is equal to string(2) -> did not trigger any emails (Flow succeeded, but result is False).
I tried [Days Until Due] is equal to 2 -> did not trigger any emails (Flow succeeded, but result is False).
I tried [Days Until Due] is equal to int(2) -> did not trigger any emails (Flow succeeded, but result is False).
Any other suggestions are appreciated!